Installed 15,000 sqf of TN220 composite at north end of CAMU; CAMU 97% lined; Heavy rains forecasted;
Installed 27,852 sqf of HDPE at north end of CAMU;
Heavy Rain; Continue to dewater, re-grade, and dry remaining waste surface for installation of remaining CAP;
Prepare waste surface (re-grade/dry) for installation of remaining CAP on former TSWRB (pending weather);
Rain; Limited Envirocon crew onsite to maintain dewatering pumps;
Install geomembrane panels and geocomposite on former TSWRB to the extent conditions would allow;
Install geomembrane panels on former TSWRB to the extent conditions would allow;
Prepare waste surface (re-grade/dry) for installation of CAP on former TSWRB;