Posted July 13, 2011 Daily Report for Friday July 8, 2011

Installed 15,000 sqf of TN220 composite at north end of CAMU; CAMU 97% lined; Heavy rains forecasted;


Posted July 13, 2011 Daily Report for Thursday July 7, 2011

Installed 27,852 sqf of HDPE at north end of CAMU;


Posted July 13, 2011 Daily Report for Wednesday July 6, 2011

Heavy Rain; Continue to dewater, re-grade, and dry remaining waste surface for installation of remaining CAP;


Posted July 8, 2011 Daily Report for Tuesday July 5, 2011

Prepare waste surface (re-grade/dry) for installation of remaining CAP on former TSWRB (pending weather);


Posted July 8, 2011 Daily Report for Monday July 4, 2011

Rain; Limited Envirocon crew onsite to maintain dewatering pumps;


Posted July 8, 2011 Daily Report for Sunday July 3, 2011

Install geomembrane panels and geocomposite on former TSWRB to the extent conditions would allow;


Posted July 8, 2011 Daily Report for Saturday July 2, 2011

Install geomembrane panels on former TSWRB to the extent conditions would allow;


Posted July 8, 2011 Daily Report for Friday July 1, 2011

Prepare waste surface (re-grade/dry) for installation of CAP on former TSWRB;